STEP
|
ACTIVITY |
DATE |
1
|
Research and Agency Consultation |
9/04 - 1/05 |
2
|
Agency Consultation Meeting - Anchorage |
10/22/04 |
3
|
Prepare required revisions to remaining elements
of the 2003 Public Hearing Draft |
11/04 - 3/05 |
4
|
Public
Hearing Draft is Released for 30-day Public Review and Comment
Period; Unalaska Planning Commission Briefed |
3/3/05 |
5
|
30-Day Public Comment Period Closes |
4/1/05 |
6
|
Obtain Resolutions of Support
from City Council and Traditional Village Councils |
5/05 |
7
|
Prepare Submittal for State |
6/05-7/05 |
|
Submit Final Draft Plan Amendment |
11/21/05 |
|
Submit additional information |
12/18/05 |
|
DNR releases plan and preliminary recommendations
for public review |
March 2006 |
|
AWCRSA modifies plan |
May 2006 |
12
|
DNR Commissioner's Decision to Approve |
July 2006 |